Rumara Engineering is one of the best process design engineering consultant in mumbai. We have staffs with 18 years of experience.

Rumara Engineering’s function is to provide Design Engineering Services / Consultancy to Engineering Organizations and Operating Companies at various stages of the project execution.

Our core objective is to provide process design engineering consultation/solutions to the clients who are :

Mission

To provide responsive, safe and trusted solution to clients with the highest quality and cost- effective engineering and design services in the industry while maintaining ethical standards

Rumara Engineering

We are ISO 9001:2015 ISO Certified and MSME registered company. We have established our office in Vashi, Navi Mumbai.
GST Number: 27AOXXPP8040C1ZK

Let's have a cup of tea with the team

15000 +
Number of Man Hour Completed Per Year
60 +
Number of Project Successfully Completed

Services We Provide

Look into our hand full of areas we cater in our process design consulting service. 

Basic Process Engineering

Process Safety Analysis

Mechanical Engineering

Detailed Process Engineering

Water
Treatment

Piping Engineering

E&I
Engineering

PFD & P&ID Drafting

Why Choose Us?

We are one of the best process design engineering consultant in mumbai. Feel Free to contact us anytime you want via email or direct phone call. We will be happy to help you. 

worker
Quality Engineering
group
Global Experience Team
Cost Effective Solutions
Cost Effective Solutions
Employee Development
Employee Development
Strong Client Relations
Strong Client Relations
Flexible Working Style
Flexible Working Style
We Value Employee Contribution
We Value Employee Contribution
ISO 9001:2015 Certified
ISO 9001:2015 Certified
All Size Projects
All Size Projects

Let have a cup of tea with rumara Engineering

We can make your vision come true!

Our Clients

*To get more information you can contact us and set up a meeting*

Rumara Office

SUMMARY OF PROJECTS BY RUMARA

Sr. No.ActivityPast ProjectsType of ProjectDuration of Project
1Piping and Instrumentation Diagram (P&ID): Consistency check between Drafted and Master P&IDs1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. Complete Basic and Detailed Engineering of Methanol Recovery System
3. Complete Basic and Detailed Engineering of Butyl Ether
4. FEED Verification for Crude Oil and Associated System
5. FEED Engineering for LNG and LPG System
6. P&ID checking
7. Detailed Engineering of Ammonia and Castor Oil System
8. Steam and Condensate system of Boiler
9. Drum Filling System of Iso-Butyl Alcohol and n-Butyl Alcohol
10. Review and comments on Furnace system of FCCU Unit
1. LSTK Project
2. Basic and Detailed Engineering
3. Basic and Detailed Engineering
4. FEED Level
5. FEED Level
6. Detailed Engineering Activity
7. Detailed Engineering
8. Detailed Engineering Activity
9. Detailed Engineering Activity
10. Detailed Engineering Activity
1. 6 months and Ongoing
2. 3 month
3. 5 months
4. 3 months
5. 2 month and Ongoing
6. 1 month
7. 6 months
8. 1 month
9. 2 months
10. 1 week
2Consistency check between P&ID and Isometrics1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. Utility Pump Hydraulic Calculations
1. LSTK Project
2. Detailed Engineering Activity
1. 6 months and Ongoing
2. 2 months
3Line Hydraulic Calculation (Single phase/ Two Phase) with Isometric Drawings1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit) (400 lines)
2. Complete Basic and Detailed Engineering of Methanol Recovery System (200 lines)
3. Complete Basic and Detailed Engineering of Butyl Ether (300 lines)
4. Detailed Engineering of Ammonia and Castor Oil System (100 lines)
5. FEED Verification for Crude Oil and Associated System (150 lines)
6. Utility Network Model (Cooling Water, Brine, Chilled Water and Waste Water) using AFT Fathom
7. FEED Engineering for LNG and LPG System
1. LSTK Project
2. Basic and Detailed Engineering
3. Basic and Detailed Engineering
4. Detailed Engineering
5. FEED Level
6. Detailed Engineering Activity
7. FEED Level
1. 6 months and Ongoing
2. 3 months
3. 5 months
4. 6 months
5. 3 months
6. 3 months
7. 2 month and Ongoing
4Pump hydraulics Calculation1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. Complete Basic and Detailed Engineering of Methanol Recovery System
3. Complete Basic and Detailed Engineering of Butyl Ether
4. Detailed Engineering of Ammonia and Castor Oil System
5. FEED Verification for Crude Oil and Associated System
6. Utility Pump Hydraulic Calculations
7. FEED Engineering for LNG and LPG System
1. LSTK Project
2. Basic and Detailed Engineering
3. Basic and Detailed Engineering
4. Detailed Engineering
5. FEED Level
6. Detailed Engineering Activity
7. FEED Level
1. 6 months and Ongoing
2. 3 months
3. 5 months
4. 6 months
5. 3 months
6. 2 months
7. 2 month and Ongoing
5Control valve sizing1. FEED Verification for Crude Oil and Associated System
2. Utility Pump Hydraulic Calculations
3. Complete Basic and Detailed Engineering of Butyl Ether
4. FEED Engineering for LNG and LPG System
1. FEED Level
2. Detailed Engineering Activity
3. Basic and Detailed Engineering
4. FEED Level
1. 3 months
2. 2 months
3. 5 months
4. 2 months and Ongoing
6Heat Exchanger Thermal Calculation (Data entry)1. Complete Basic and Detailed Engineering of Methanol Recovery System
2. Complete Basic and Detailed Engineering of Butyl Ether
3. FEED Engineering for LNG and LPG System
1. Basic and Detailed Engineering
2. Basic and Detailed Engineering
3. FEED Level
1. 3 months
2. 5 months
3. 2 months and Ongoing
7PSV Sizing Calculation1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. FEED Verification for Crude Oil and Associated System
3. Complete Basic and Detailed Engineering of Methanol Recovery System
4. Complete Basic and Detailed Engineering of Butyl Ether
5. FEED Engineering for LNG and LPG System
1. LSTK Project
2. FEED Level
3. Basic and Detailed Engineering
4. Basic and Detailed Engineering
5. FEED Level
1. 6 months and Ongoing
2. 3 months
3. 3 months
4. 5 months
5. 2 month and Ongoing
8Vessel Sizing1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. FEED Verification for Crude Oil and Associated System
3. Complete Basic and Detailed Engineering of Methanol Recovery System
4. Complete Basic and Detailed Engineering of Butyl Ether
5. FEED Engineering for LNG and LPG System
6. Vessel Datasheet Preparation and Updation for Isomer Process Unit
1. LSTK Project
2. FEED Level
3. Basic and Detailed Engineering
4. Basic and Detailed Engineering
5. FEED Level
6. Detailed Engineering Activity
1. 6 months and Ongoing
2. 3 months
3. 3 months
4. 5 months
5. 2 month and Ongoing
6. 1 month
9Tank Sizing1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. Complete Basic and Detailed Engineering of Methanol Recovery System
3. Complete Basic and Detailed Engineering of Butyl Ether
4. FEED Verification for Crude Oil and Associated System
1. LSTK Project
2. Basic and Detailed Engineering
3. Basic and Detailed Engineering
4. FEED Level
1. 6 months and Ongoing
2. 3 months
3. 5 months
4. 3 months
11Surge AnalysisSurge analysis for Cooling water network for Glass lined exchangers ( by leased based AFT Impulse)Special Studies3 months
10AFT Fathom Network Hydraulic (Steady State)Utility Network Model (Cooling Water, Brine, Chilled Water and Waste Water) using AFT FathomSpecial Studies3 months
11Instrument datasheet Preparation1. Instrument Datasheet Preparation for Crude Dewaxing Unit
2. Complete Basic and Detailed Engineering of Methanol Recovery System
3. Complete Basic and Detailed Engineering of Butyl Ether
4. Detailed Engineering of Ammonia and Castor Oil System
5. FEED Verification for Crude Oil and Associated System
1. Detailed Engineering Activity
2. Basic and Detailed Engineering
3. Basic and Detailed Engineering
4. Detailed Engineering
5. FEED Level
1. 1 month
2. 3 months
3. 5 months
4. 6 months
5. 3 months
12Line list1. Complete Basic and Detailed Engineering of Methanol Recovery System
2. Complete Basic and Detailed Engineering of Butyl Ether
3. FEED Verification for Crude Oil and Associated System
4. FEED Engineering for LNG and LPG System
1. Basic and Detailed Engineering
2. Basic and Detailed Engineering
3. FEED Level
4. FEED Level
1. 3 months
2. 5 months
3. 3 months
4. 2 months and Ongoing
13Equipment list1. Complete Basic and Detailed Engineering of Methanol Recovery System
2. Complete Basic and Detailed Engineering of Butyl Ether
3. FEED Verification for Crude Oil and Associated System
4. FEED Engineering for LNG and LPG System
1. Basic and Detailed Engineering
2. Basic and Detailed Engineering
3. FEED Level
4. FEED Level
1. 3 months
2. 5 months
3. 3 months
4. 3 months and Ongoing
14Hazardous Area Classification1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. FEED Engineering for LNG and LPG System
1. LSTK Project
2. FEED Level
1. 6 months and Ongoing
2. 3 months and Ongoing
15Operating ManualFEED Engineering for LNG and LPG SystemFEED Level3 months and Ongoing
16HAZOP Study and Closeout1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit) - Participation and Closeout of Recommmendation
2. Chairing of HAZOP Study for Bio-Gas System
1. LSTK Project
2. Special Studies
1. 6 months and Ongoing
2. 1 Week
17SIL Study1. Field Gas Gathering Station (FGGS and Gas Dehydration Unit)
2. SIL Assessment (SIF Identification and Hand Switches)
1. LSTK Project
2. Special Studies
1. 6 months and Ongoing
2. 1 month
18Safety Study
1.Emergency Isolation Valve Study
2. IPL Assessment
3. LO/LC Assessment
Multiple International Sites of our reputed clientSpecial Studies3 months to 8 months